TN 27. February 2026
The Lodge Hotel, Castle Square in Ludlow acheives B energy rating, which is fantastic for a grade 1 listed building built in the 1500s.
The Challenge
The Lodge required:
The solution needed to deliver performance and efficiency while respecting the constraints of a heritage building.
The Solution
At the heart of the installation are high-efficiency condensing natural gas boilers connected to three large buffer vessels. Each buffer incorporates stainless steel hot water production coils, solar heat exchanger coils, immersion backup provision, and multiple temperature sensors to optimise performance.
Rather than storing domestic hot water, the system produces it instantly on demand via stainless steel coils within the buffers. This approach improves hygiene, reduces standing losses, and ensures rapid response to fluctuating demand.
With a total boiler capacity of 160kW, the system can deliver up to 6,000 litres per hour of continuous hot water draw-off, comfortably meeting peak hotel usage.
Solar Thermal Integration
To reduce reliance on gas and improve sustainability, five banks of evacuated solar thermal tubes feed dedicated solar coils within the buffers. The system includes solar heat metering and intelligent pump speed control to maximise renewable contribution whenever conditions allow.
Solar integration supports lower fuel consumption and long-term operational savings while aligning with clean energy objectives.
Zoned Heating Control
Heating is divided into ten independently controlled zones across the ground, first, and second floors. Each zone benefits from:
This ensures balanced comfort throughout the building while minimising unnecessary energy use.


Domestic Hot Water Hygiene & Circulation
Given the multi-floor layout, effective circulation and hygiene control were critical.
Thermostatic circulation regulators balance the hot water return circuits, ensuring consistent temperatures at all outlets. A time-controlled Legionella protection cycle runs automatically each week, raising system temperatures to sterilisation levels to ensure full compliance and guest safety.
Intelligent System Management
The entire installation is managed via the HDG Control system, comprising of an intuitive touch-screen interface supported by remote app access. The control platform integrates boiler operation, buffer management, solar input, heating circuits, and domestic hot water production into one intelligent system.
Time scheduling, demand control, and real-time system data ensure maximum efficiency and ease of operation for hotel management.
The Outcome
The completed installation provides Ludlow Castle Lodge with:
This project demonstrates Zeroridge Consulting’s ability to deliver sophisticated, energy-efficient heating and hot water solutions tailored to complex hospitality environments, combining performance, sustainability, and long-term reliability in a heritage setting.